Anticipated Project Timeline
The proposed schedule of completion for the Southeast Connector (SE Connector) is as follows:
PHASE I
SW 2nd Street to SE 15th Street |
PHASE II
SE 15th Street to U.S. 65 |
- December 16, 2010 Ribbon Cutting
- SW 2nd to SE 9th Open to Traffic
|
- Record of Decision approved for selected alternative
|
- Street Design SE 9th - SE 15th
|
- Preliminary Engineering & Analysis SE 15th – SE 30th
|
- Utility Relocations / Site Preparation
SE 9th – SE 15th
- Negotiate Railroad Agreements
|
- R/W Acquisitions SE 15th – SE 30th
- Bridge Design
- Final Design SE 15th – SE 30th
- Negotiate Railroad Agreements
|
- Start Street Construction SE 9th – SE 15th
|
- Start Roadway & Bridge Construction SE 15th – SE 30th
|
- Construction SE 9th - SE 15th
|
- Construction SE 15th – SE 30th
|
- Finish Construction
SE 9th – SE 15th
|
- Finish Roadway & Bridge Construction
SE 15th – SE 30th
|
Future Activities – Design, R/W, Utility Relocations and Construction of SE 30th – Hwy 65
|