Project Overview
Background
Project History
Study Area & Maps
Project Team
Timeline
 
Information Center
Newsletters
Press Releases
TIGER Grant
Related Web Links
Image Gallery
 
Get Involved
Citizen's Guide
Business Kits
Public Meetings
Advisory Groups
Mailing List
Contact Us

Anticipated Project Timeline

The proposed schedule of completion for the Southeast Connector (SE Connector) is as follows:

PHASE I
SW 2nd Street to SE 15th Street

PHASE II
SE 15th Street to U.S. 65

2005

  • Re-evaluation of existing Environmental Impact Statement (EIS)
  • Pre-design studies for:
    • Traffic Forecasts and Analysis
    • Land Use Planning
    • River Hydraulics
    • Storm Drainage
    • Sanitary Sewers

2005

  • Initiate project with state and local agencies
  • Develop study Purpose & Need
  • Develop and screen preliminary alternatives
  • Begin environmental analysis
  • Begin preliminary engineering
  • Kickoff meetings with advisory groups
  • First Open House

2006

  • Des Moines River Crossing Bridge Concept
  • Street Design SW 2nd to SE 6th
  • Bridge Design
  • R/W Acquisitions SW 2nd to SE 6th
  • Utility Relocations SW 2nd to SE 6th
  • Levee Relocation Design

2006

  • Continue preliminary engineering
  • Continue environmental analysis
  • Coordination with state and local agencies, and advisory groups
  • Continue gathering public input
  • Identify reasonable alternatives

2007

  • Street Design SW 2nd to SE 6th
  • Continue Bridge Design
  • Continue R/W Acquisitions
  • Continue Utility Relocations
  • Start Bridge Construction (Fall)
  • R/W Acquisitions SE 6th to SE 12th
  • Utility Relocations SE 6th to SE 12th

2007

  • Continue preliminary engineering and analysis
  • Continue agency coordination and public involvement
  • Screen reasonable alternatives

2008

  • Start Bridge Construction
  • Street Design SW 2nd to SE 4th
  • Street Design SE 4th to SE 9th

2008

  • Prepare and distribute Draft EIS
  • Public Hearing
  • Public comment and review period

2009

  • Start Street Construction SW 2nd to SE 4th
  • Start Street Construction SE 4th to SE 9th

2009

  • Prepare and Distribute Final EIS
  • Public Hearing
  • Public comment and review period

2010

  • Complete Bridge Construction
  • Complete Street Construction SW 2nd to SE 4th
  • Complete Street Construction SE 4th to SE 9th
  • Continue Street Design SE 9th to SE 15th
  • R/W Acquisitions SE 12th to SE 15th
  • Utility Relocations SE 12th to SE 15th

 

2010

  • Receive Record of Decision for selected alternative

Future Activities

  • Preliminary and Final Design of Selected Alternatives
  • Design, R/W Acquisition, Utility Relocation and Construction of continuing sections
  • Construction of SE Connector beyond SE 15th