Anticipated Project Timeline

The proposed schedule of completion for the Southeast Connector (SE Connector) is as follows:

PHASE I
SW 2nd Street to SE 15th Street

PHASE II
SE 15th Street to U.S. 65

2005

  • Re-evaluation of existing Environmental Impact Statement (EIS)
  • Pre-design studies for:
    • Traffic Forecasts and Analysis
    • Land Use Planning
    • River Hydraulics
    • Storm Drainage
    • Sanitary Sewers

2005

  • Initiate project with state and local agencies
  • Develop study Purpose & Need
  • Develop and screen preliminary alternatives
  • Begin environmental analysis
  • Begin preliminary engineering
  • Kickoff meetings with advisory groups
  • First Open House

2006

  • Des Moines River Crossing Bridge Concept
  • Street Design SW 2nd to SE 6th
  • Bridge Design
  • R/W Acquisitions SW 2nd to SE 6th
  • Utility Relocations SW 2nd to SE 6th

2006

  • Continue preliminary engineering
  • Continue environmental analysis
  • Coordination with state and local agencies, and advisory groups
  • Continue gathering public input
  • Identify reasonable alternatives

2007

  • Continue Design SW 2nd to SE 6th
  • Continue Bridge Design
  • Continue R/W Acquisitions
  • Continue Utility Relocations
  • Start Bridge Construction (Fall)
  • Start Design SE 6th to SE 15th
  • R/W Acquisitions SE 6th to SE 15th
  • Utility Relocations SE 6th to SE 15th

2007

  • Continue preliminary engineering and analysis
  • Continue agency coordination and public involvement
  • Screen reasonable alternatives
  • Prepare and distribute Draft EIS
  • Public Hearing
  • Public comment and review period
  • Address public and agency comments

2008

  • Continue Bridge Construction
  • Street Construction SW 2nd to SE 6th
  • Continue Design SE 6th to SE 15th
  • R/W Acquisitions SE 6th to SE 15th
  • Utility Relocations SE 6th to SE 15th

2008

  • Prepare and distribute Final EIS
  • Receive Record of Decision for selected alternative

2009 – 2012

  • Complete Bridge Construction
  • Complete Street Construction SW 2nd to SE 6th
  • Street Construction SE 6thto SE 15th

Future Activities (Dependent on Funding)

  • Preliminary and Final Design of Selected Alternative
  • Design, R/W acquisition, Utility Relocation and Construction of continuing sections
  • Construction of SE Connector beyond SE 15th Street